Under construction

ARAMUS COMPLEX

by GURUKRUPA GROUP BUILDERS AND DEVELOPERS

PLOT NO.87, SECTOR-21, Panvel, 400707

Dec 2019
Possession
74.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 74.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.

Official RERA facts

Registration
P52000007602
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019originally December 2018
Construction
74.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Open Parking54%

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of ARAMUS COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ARAMUS COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.