Prakriti Park-Chandan (C Wing)

by Khwaish Enterprises

153/3/3, Panvel, 410206

Dec 2028
Possession
29.1%
Built
2
Complaints
96
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2023, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52000007771
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally December 2023
Construction
29.1% complete
Units sold
23 of 96

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
14
Unit mix
82 res ยท 14 comm
Architect
Destination Architecture Interiror Designs

Buyer community

Connect with other buyers and owners of Prakriti Park-Chandan (C Wing) โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Prakriti Park-Chandan (C Wing). Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.