Under construction

SHIV UTSAV

by MARUTI ENTERPISES

150/12/A/3 AND 150/12/B AND 151/5 P, Pashane, 421503

Mar 2025
Possession
86.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 86.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.

Official RERA facts

Registration
P52000007812
Status
Ongoing
Stage
Certificate Signed
Possession
March 2025originally March 2024
Construction
86.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of SHIV UTSAV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIV UTSAV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.