Under construction

SURYA GALAXY PHASE I

by SHUBH LAXMI REALTY

38/1, 38/2, KARJAT, 410101

Jul 2022
Possession
100%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jan 2021, now proposed Jul 2022 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2022 per the RERA filing.

Official RERA facts

Registration
P52000009302
Status
Ongoing
Stage
Certificate Signed
Possession
July 2022originally January 2021
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SURYA GALAXY PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SURYA GALAXY PHASE I. Real notes from real buyers beat any brochure.

Start a discussion