Under construction

Olympeo Riverside - Phase 3

by Olympeo Riverside Projects LLP

48/9, 48/10A/1, Neral, 410101

Dec 2028
Possession
15.5%
Built
6
Complaints
360
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Jun 2022, now proposed Dec 2028 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52000012184
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally June 2022
Construction
15.5% complete
Units sold
191 of 360

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths26%
Water Supply31%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting26%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water10%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2017
Floors
8
Unit mix
360 res ยท 0 comm
Architect
Sakshi Vinayak Khanorkar

Buyer community

Connect with other buyers and owners of Olympeo Riverside - Phase 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Olympeo Riverside - Phase 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.