OBELISK
by SHREE CHINMAY GAURANG INFRASTRUCTURE
SUB PLOT NO. 11, SURVEY NO.746/1A,746/1B,746/2A,746/2B,746/2B/1C, PANVEL, 410206
- Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 87.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Official RERA facts
- Registration
- P52000016196
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2025originally March 2024
- Construction
- 87.3% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Apr 2018
- Floors
- 14
- Architect
- 07 Associates
Buyer community
Connect with other buyers and owners of OBELISK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OBELISK. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.