PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

RAJ BAUG PHASE - III

by NEHALDHARA REALTORS

SURVEY NO 44 AND 45, CTS NO 78 AND 79A, MAHESH THEATRE, 410101

Dec 2026
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000016233
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2018
Floors
5

Buyer community

Connect with other buyers and owners of RAJ BAUG PHASE - III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAJ BAUG PHASE - III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.