ETERNIA SPACE PHASE II

by PLANET SPACE

SURVEY 20-1 A 20-1 B, KARJAT, 410201

Dec 2026
Possession
99.1%
Built
2
Complaints
279
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000020402
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
99.1% complete
Units sold
192 of 279

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2019
Floors
9
Unit mix
273 res ยท 6 comm
Architect
NEHA JAIN

Buyer community

Connect with other buyers and owners of ETERNIA SPACE PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ETERNIA SPACE PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.