AAIJI RESIDENCY

MahaRERA P52000022005High risk

by OM SAI DEVELOPERS

PLOT NO 153A, PANVEL, 410206

Official record
Dec 2022
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.

Promoter

Builder profile

Builder
OM SAI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000022005
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2019
Floors
8

Buyer community

Connect with other buyers and owners of AAIJI RESIDENCY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching AAIJI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.