PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Belmac Riverside - III A BLDG

by SUPREME HOLDINGS & HOSPITALITY (INDIA) LIMITED

GAT NO. 99/1, 99/2/1, 99/2/2, 99/3/1, Akurli Village, 410206

Aug 2024
Possession
81.8%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 81.8%.

Official RERA facts

Registration
P52000022972
Status
New
Stage
Certificate Signed
Possession
August 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Nov 2019
Floors
7

Buyer community

Connect with other buyers and owners of Belmac Riverside - III A BLDG โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Belmac Riverside - III A BLDG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.