Sakasi Park III

by Jindal Builders and Developers

G.No 16, Village Akurli, Akurli, 410206

Dec 2023
Possession
90.9%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.9%.

Official RERA facts

Registration
P52000023426
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC1250409520 Nov 2025
    Suhas Jadhav vs Jindal Builders and Developers

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Dec 2019
Floors
5

Buyer community

Connect with other buyers and owners of Sakasi Park III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sakasi Park III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.