PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DEEP MIRACLE

by SAMBHAV REALITIES

PLOT NO 248, PUSHPAK (NEW), 410206

Jun 2025
Possession
89.4%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 89.4%.

Official RERA facts

Registration
P52000026825
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
89.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started

Building & registration

RERA registered
Oct 2020
Floors
8

Buyer community

Connect with other buyers and owners of DEEP MIRACLE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DEEP MIRACLE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.