K K RESIDENCYMahaRERA P52000027162

by SHREE SAI HOME MAKERS

377 378/A 382 382/A 382/B 389 390/A 390/B 391/A 391/B 392/A 392/B 393 394 395/A 395/B 396 397/A 397/B 398/A 398/B 399 586/A 586B, PANVEL, 410208

Sept 2026
Possession
43.1%
Built
0
Complaints
142
Units
High risk
  • Behind schedule. Possession is due Sept 2026 but construction is only at 43.1%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52000027162
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
43.1% complete
Units sold
20 of 142

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2020
Floors
5
Unit mix
129 res ยท 13 comm

Buyer community

Connect with other buyers and owners of K K RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching K K RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.