SAI SANSKRUTI

MahaRERA P52000028651High risk

by Shree Sai Builders and Developers

PLOT NO 18 SECTOR 24, PUSHPAK NEW, 410206

Official record
Jun 2024
Possession
41.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 41.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Promoter

Builder profile

Builder
Shree Sai Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000028651
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
41.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2021
Floors
6

Buyer community

Connect with other buyers and owners of SAI SANSKRUTI — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SAI SANSKRUTI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.