Under construction

RUBY CORNERMahaRERA P52000029369

by TAUSEEF SHAMSHULHUDA KHAN

B-93, ULWE, RAIGAD, 410206

Sept 2021
Possession
36.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2021) has passed with construction at 36.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2021 per the RERA filing.

Official RERA facts

Registration
P52000029369
Status
New
Stage
Certificate Signed
Possession
September 2021
Construction
36.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2021
Floors
6

Buyer community

Connect with other buyers and owners of RUBY CORNER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RUBY CORNER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.