PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GANGA SHANKAR HEIGHTSMahaRERA P52000029379

by Vikrant Anil Turekar

Plot No -213, Pushpak New, 410206

Sept 2026
Possession
43.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2023, now proposed Sept 2026 per the RERA filing.
  • Behind schedule. Possession is due Sept 2026 but construction is only at 43.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52000029379
Status
New
Stage
Certificate Signed
Possession
September 2026originally September 2023
Construction
43.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2021
Floors
8

Buyer community

Connect with other buyers and owners of GANGA SHANKAR HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GANGA SHANKAR HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.