J K PARAMOUNT
by J.K.INFRA BUILDERS & DEVELOPERS
PLOT NO. 296, PUSHPAK NODE, 410206
May 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (May 2023) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2023 per the RERA filing.
Official RERA facts
- Registration
- P52000029517
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2023
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jun 2021
- Floors
- 6
Buyer community
Connect with other buyers and owners of J K PARAMOUNT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching J K PARAMOUNT. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.