Under construction

OVI ENCLAVEMahaRERA P52000031985

by STATUS REALTOR

CTS NO 1097/A/1, SURVEY NO 32/6, CHINCHAVLI-SHEKIN, LOWJEE, KHOPOLI, 410203

May 2027
Possession
81.8%
Built
0
Complaints
31
Units
Caution
  • Possession delayed ~3 yrs. Originally promised May 2024, now proposed May 2027 per the RERA filing.

Official RERA facts

Registration
P52000031985
Status
New
Stage
Certificate Signed
Possession
May 2027originally May 2024
Construction
81.8% complete
Units sold
23 of 31

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lighting50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2021
Floors
7
Unit mix
24 res ยท 7 comm
Architect
KISHOR VITHAL SHINDE

Buyer community

Connect with other buyers and owners of OVI ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OVI ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.