AMBA RESIDENCYMahaRERA P52000032513

by N R Builders And Developers

S. NO. 79, H. NO.2A/ 1/1, 2B.1/2 2A/1 2B/1/1 PLOT NO. 5, SHANTI NAGAR, 402106

Dec 2028
Possession
57.3%
Built
0
Complaints
41
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52000032513
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2025
Construction
57.3% complete
Units sold
9 of 41

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water50%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2022
Floors
9
Unit mix
41 res ยท 0 comm
Architect
Manajit S Mohite

Buyer community

Connect with other buyers and owners of AMBA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMBA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.