Under construction
Brajesh SapphireMahaRERA P52000033994
Survey No -23/2/C, Panvel, 410206
Jun 2025
Possession
63.6%
Built
0
Complaints
38
Units
Caution
- Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 63.6%.
Official RERA facts
- Registration
- P52000033994
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2025originally June 2024
- Construction
- 63.6% complete
- Units sold
- 20 of 38
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths90%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains80%
Landscaping & Tree Planting80%
Street Lightingnot started
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Building & registration
- RERA registered
- Mar 2022
- Floors
- 6
- Unit mix
- 38 res ยท 0 comm
- Architect
- Swapnil Kalyankar Architects
Buyer community
Connect with other buyers and owners of Brajesh Sapphire โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Brajesh Sapphire. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.