RIVER VALLEYMahaRERA P52000048028

by MOHD SHOEB MAKKI

PLOT NO. 70 & 71 CTS NO 1602, 1605, 1606, 1607, 1608 S NO 62+61+60 H NO. 10+7+5A+2+0, DP ROAD, 410203

Dec 2026
Possession
60%
Built
0
Complaints
0
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000048028
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
60% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2022
Floors
8

Buyer community

Connect with other buyers and owners of RIVER VALLEY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RIVER VALLEY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.