SM EMERALDMahaRERA P52000051962

by S M HITECH DEVELOPERS

SURVEY NO.-112/5/1(Pt), TALOJA, 410208

Dec 2027
Possession
54.5%
Built
0
Complaints
198
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52000051962
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
54.5% complete
Units sold
124 of 198

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2023
Floors
11
Unit mix
168 res ยท 30 comm

Buyer community

Connect with other buyers and owners of SM EMERALD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SM EMERALD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.