NIRMALA PARKMahaRERA P52000053561

by CYRIL DUMING DSOUZA

S.NO 240 (215) HISSA NO 2/4, ROHA, 402116

Apr 2027
Possession
34%
Built
0
Complaints
69
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 34%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P52000053561
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
34% complete
Units sold
6 of 69

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)4%
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2023
Floors
7
Unit mix
60 res ยท 9 comm
Architect
VASTU CONSULTANT AND ENGINEER

Buyer community

Connect with other buyers and owners of NIRMALA PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRMALA PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.