Under construction

Harmony ResidencyMahaRERA P52000054988

by Harmony Realtors

Plot No- 7A, Sector- 54, Dronagiri, Dronagiri, 400702

Mar 2027
Possession
45.7%
Built
0
Complaints
56
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 45.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52000054988
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
45.7% complete
Units sold
11 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Feb 2024
Floors
8
Unit mix
56 res ยท 0 comm
Architect
Atul Patel Architects

Buyer community

Connect with other buyers and owners of Harmony Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Harmony Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.