All RERA projects
๐๏ธ
Under construction
ELCARIM ENCLAVEMahaRERA P52000055614
by ELCARIM DEVELOPERS AND PROPERTIES PRIVATE LIMITED
SURVEY NO. 60, MAMDAPUR, 410101
Dec 2026
Possession
35.7%
Built
0
Complaints
91
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 35.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000055614
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 35.7% complete
- Units sold
- 26 of 91
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Apr 2024
- Floors
- 8
- Unit mix
- 91 res ยท 0 comm
- Architect
- THE DESIGN INDIA GROUP
Buyer community
Connect with other buyers and owners of ELCARIM ENCLAVE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ELCARIM ENCLAVE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.