PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SaffronSuites Alibaug - 9MahaRERA P52000077517

by SAFFRONSUITES PRIVATE LIMITED

Gat No. 17, Mhatroli, 402209

Dec 2029
Possession
9.1%
Built
0
Complaints
55
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2027, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P52000077517
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2027
Construction
9.1% complete
Units sold
0 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2024
Floors
12
Unit mix
55 res ยท 0 comm
Architect
Abhijit S Mohite Mohite

Buyer community

Connect with other buyers and owners of SaffronSuites Alibaug - 9 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SaffronSuites Alibaug - 9. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.