Under construction

Dreams Avani C wingMahaRERA P52100000157

by Dreams Corporation Pvt Ltd

70 B / 2/1, Manjari, 412307

Oct 2021
Possession
65.9%
Built
8
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Oct 2021 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 65.9%.

Official RERA facts

Registration
P52100000157
Status
Ongoing
Stage
Certificate Signed
Possession
October 2021originally June 2019
Construction
65.9% complete
Units sold
0 of 0

RERA complaint record8 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcnt67%
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacedone
Open Parking90%

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of Dreams Avani C wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Dreams Avani C wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.