KALPAK HOMES KIRKATWADI PHASE IIMahaRERA P52100000741

by SHUBHANKAR DEVELOPERS

GAT NO. 199,200,201,202 AND 265 PART, KIRKATWADI, 411024

Mar 2024
Possession
87.3%
Built
7
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Mar 2024 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 87.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.

Official RERA facts

Registration
P52100000741
Status
Ongoing
Stage
Certificate Signed
Possession
March 2024originally December 2019
Construction
87.3% complete
Units sold
0 of 0

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths44%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water25%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
11

Buyer community

Connect with other buyers and owners of KALPAK HOMES KIRKATWADI PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KALPAK HOMES KIRKATWADI PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.