All RERA projects
๐๏ธ
Under construction
KALPAK HOMES KIRKATWADI PHASE IIMahaRERA P52100000741
GAT NO. 199,200,201,202 AND 265 PART, KIRKATWADI, 411024
Mar 2024
Possession
87.3%
Built
7
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Mar 2024 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 87.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.
Official RERA facts
- Registration
- P52100000741
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2024originally December 2019
- Construction
- 87.3% complete
- Units sold
- 0 of 0
RERA complaint record7 records
- ComplaintCC0050000004714978 Aug 2024Pramod Baburao Hingane vs Shubhankar Kalpak Builders Pvt LtdOrder of Pramod Hingane.pdf on MahaRERA
- ComplaintCC00500000006487329 Nov 2020Rohit Vinayak Joshi vs Shubhankar Developers1.pdf on MahaRERA
- ComplaintCC0050000000646902 Oct 2020Babita Bhagchand Jadhav vs Sameer Sharatchandra BelvalkarCC005_64690.pdf on MahaRERA
- Misc. applicationCC0050000000646902 Oct 2020Babita Bhagchand Jadhav vs Sameer Sharatchandra BelvalkarCC005_64690.pdf on MahaRERA
- ComplaintCC0050000000646141 Oct 2020Rajendra Shankar Phalke and Mrs. Archana Rajendra Phalke vs M/s. Shubhankar Developers through its Partner Sameer Sharatchandra Belvalkar02_Order_64614 signed.pdf on MahaRERA
- ComplaintCC0050000000539926 Feb 2020Bhagwan Ramchanra Gawali vs M/s Shubhankar Developers1o.pdf on MahaRERA
- ComplaintCC0050000000334821 Oct 2019Mr. Kalidas Vasant Yenpure vs M/s. Shubhankar DevelopersCC005_33482 Final Order.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths44%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water25%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 11
Buyer community
Connect with other buyers and owners of KALPAK HOMES KIRKATWADI PHASE II โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KALPAK HOMES KIRKATWADI PHASE II. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.