All RERA projects
๐๏ธ
Under construction
SEYA
by SEYA PATE CONSTRUCTIONS LLP
S NO 120A 120B F P NO 545 P NO 18, SINHAGAD ROAD, 411009
Mar 2022
Possession
43.6%
Built
7
Complaints
0
Units
High risk
- Recovery warrants issued. MahaRERA has issued 2 recovery warrants against this project โ the strongest enforcement action on record.
- Possession delayed ~1 yr. Originally promised Sept 2020, now proposed Mar 2022 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 43.6%.
- Promised amenities not started. Gymnasium, Landscaped Garden are at 0% build with possession due Mar 2022 per the RERA filing.
Official RERA facts
- Registration
- P52100001129
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2022originally September 2020
- Construction
- 43.6% complete
- Units sold
- 0 of 0
RERA complaint record7 records
- Recovery warrantCC00500000016747224 Aug 2022Sandeep Avinash Zende vs Seya Pate Constructions LLP
- Misc. applicationCC00500000016747224 Aug 2022Sandeep Avinash Zende vs Seya Pate Constructions LLP
- ComplaintCC00500000016747224 Aug 2022Sandeep Avinash Zende vs Seya Pate Constructions LLPSandeep Zende Or_0001signed.pdf on MahaRERA
- Misc. applicationCC00500000009631726 Jan 2022Abhijit Bhosale vs SEYA PATE CONSTRUCTIONS LLP
- ComplaintCC00500000009631726 Jan 2022Abhijit Bhosale vs SEYA PATE CONSTRUCTIONS LLPAbhijit Bhosale Or_0001signed.pdf on MahaRERA
- Recovery warrantCC00500000009631726 Jan 2022Abhijit Bhosale vs SEYA PATE CONSTRUCTIONS LLP
- ComplaintCC00500000009632130 Nov 2021Mr Rahul Hari Mirasdar vs M/s Seya Pate Constructions LLP through its partner
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply10%
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains10%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Open Parkingnot started
WATER BODY WITH DECK10%
ATRIUM10%
GYMnot started
MINI THEATREnot started
WATCHMAN CABIN10%
Building & registration
- RERA registered
- Jul 2017
- Floors
- 15
Buyer community
Connect with other buyers and owners of SEYA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SEYA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.