Under construction

AADITYA HEIGHTS

by ANAND DEVELOPERS

C7 C8, Pune (M Corp.), 411045

Mar 2018
Possession
49.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.

Official RERA facts

Registration
P52100001408
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
49.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply68%
Sewerage (Chamber, Lines, Septic Tank , STP)68%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station25%
Open Parking68%

Building & registration

RERA registered
Jul 2017
Floors
8

Buyer community

Connect with other buyers and owners of AADITYA HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AADITYA HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.