PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

FLORISTA COUNTY

by I BUILD SUPREME UNION JV

64/3/6 3/7 3/9/2 3/9/3 3/9/4, Hadapsar, 411028

Sept 2020
Possession
90.9%
Built
6
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2018, now proposed Sept 2020 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100001416
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Jul 2017
Floors
16

Buyer community

Connect with other buyers and owners of FLORISTA COUNTY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FLORISTA COUNTY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.