All RERA projects
๐๏ธ
Under construction
The Onyx
by Vastukalp Promoters And Builders
Srvy No-186, CTS No-1155P, 1156P, 1157P, WAKAD, 411057
Dec 2022
Possession
81.8%
Built
5
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Feb 2019, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Official RERA facts
- Registration
- P52100001650
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2022originally February 2019
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record5 records
- ComplaintCC00500000016746620 Aug 2022Vinay Patel and others vs M/s. Vastukalp Promoters and Builders Through Partners Mr Hanumant Bhilare and Mr Nitin KalateIMG_0029.pdf on MahaRERA
- ComplaintCC00500000016746920 Aug 2022Shreyas Deshpande and Others vs M/s. Vastukalp Promoters and Builders Through Partners Mr Hanumant Bhilare and Mr Nitin KalateIMG_0029.pdf on MahaRERA
- Misc. applicationCC00500000016746620 Aug 2022Vinay Patel and others vs M/s. Vastukalp Promoters and Builders Through Partners Mr Hanumant Bhilare and Mr Nitin Kalate
- Misc. applicationCC00500000016746920 Aug 2022Shreyas Deshpande and Others vs M/s. Vastukalp Promoters and Builders Through Partners Mr Hanumant Bhilare and Mr Nitin Kalate
- ComplaintCC00500000007516721 Feb 2021Nilesh Prakash Bhoite vs M/s Vastukalp Promoters and Builders Through its Partner Mr. Hanumant Shankar BhilareOrder of Nilesh Bhoite- Corrected.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 27
Buyer community
Connect with other buyers and owners of The Onyx โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching The Onyx. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.