Under construction

HAZEL VIEW

by SHIV ASSOCIATES

S NO. 138/2/2/A, HINJEWADI, 411057

Nov 2020
Possession
69.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Nov 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 69.7%.

Official RERA facts

Registration
P52100001732
Status
Ongoing
Stage
Certificate Signed
Possession
November 2020originally June 2019
Construction
69.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting60%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
13

Buyer community

Connect with other buyers and owners of HAZEL VIEW โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HAZEL VIEW. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.