Under construction

Krushnai Vihar Phase-I

by Krushnai Associates

Gut No 797, Shirur, 412210

Mar 2024
Possession
90.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2020, now proposed Mar 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 90.5%.

Official RERA facts

Registration
P52100001766
Status
Ongoing
Stage
Certificate Signed
Possession
March 2024originally September 2020
Construction
90.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Landscaping & Tree Planting50%
Street Lighting70%
Water conservation /Rain water harvesting75%
Energy managemcnt70%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Open Parking60%
Fire Lift50%

Building & registration

RERA registered
Jul 2017
Floors
9

Buyer community

Connect with other buyers and owners of Krushnai Vihar Phase-I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Krushnai Vihar Phase-I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.