Mar 2027
Possession
69.8%
Built
0
Complaints
359
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100001891
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2022
- Construction
- 69.8% complete
- Units sold
- 296 of 359
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drains75%
Landscaping & Tree Planting50%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 15
- Unit mix
- 335 res ยท 24 comm
- Architect
- Y.W. Architects
Buyer community
Connect with other buyers and owners of Adhya Radha Krishna โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Adhya Radha Krishna. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.