Under construction

NOTTING HILL PHASE I

by Jaikul Associates

129P, 135/1, 138, 139, CHARHOLI, 412105

Dec 2021
Possession
81.8%
Built
4
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52100001939
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2017
Floors
3

Buyer community

Connect with other buyers and owners of NOTTING HILL PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NOTTING HILL PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.