Under construction

The One

by Shamkant Jagannath Shende

14/1, 14/2, 15/3, 15/4, Bhugaon, 412115

Dec 2020
Possession
81.8%
Built
4
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2020 per the RERA filing.

Official RERA facts

Registration
P52100001943
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Landscaping & Tree Planting75%
Street Lighting25%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Club House and Children play area25%

Building & registration

RERA registered
Jul 2017
Floors
16

Buyer community

Connect with other buyers and owners of The One โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching The One. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.