Possession
81.8%
Built
4
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2020 per the RERA filing.
Official RERA facts
- Registration
- P52100001943
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record4 records
- ComplaintCC00500000011693022 Jun 2022Rohan Arora vs Shamakant ShendeOrder of Rohan Arora_.pdf on MahaRERA
- ComplaintCC00500000012714225 May 2022Rahul Rajendra Sangar vs Shamkant Jagannath ShendeCommon Order of Bhushan, Suuhas, Rahul VS Shamkant Shende -3 complaints.pdf on MahaRERA
- ComplaintCC00500000010661124 Feb 2022bhushan hemant bonde vs shamkant shendeCommon Order of Bhushan, Suuhas, Rahul VS Shamkant Shende -3 complaints.pdf on MahaRERA
- ComplaintCC00500000010668624 Feb 2022Suuhas Deshpande vs Shamkant Jagannath ShendeCommon Order of Bhushan, Suuhas, Rahul VS Shamkant Shende -3 complaints.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths75%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Landscaping & Tree Planting75%
Street Lighting25%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Club House and Children play area25%
Building & registration
- RERA registered
- Jul 2017
- Floors
- 16
Buyer community
Connect with other buyers and owners of The One โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching The One. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.