Under construction

HILLVIEW RESIDENCY PHASE I

by KUMAR BEHARAY PROPERTIES LLP

S NO 69/5B/2, 69/8/1, 70/ 1 TO 17A1, KOTHRUD, 411038

May 2019
Possession
93.2%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (May 2019) has passed with construction at 93.2%.

Official RERA facts

Registration
P52100001962
Status
Ongoing
Stage
Certificate Signed
Possession
May 2019
Construction
93.2% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drains75%
Landscaping & Tree Planting40%
Street Lighting75%
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposal75%
Water conservation /Rain water harvesting75%
Energy managemcnt75%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
17

Buyer community

Connect with other buyers and owners of HILLVIEW RESIDENCY PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HILLVIEW RESIDENCY PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.