SOLITAIRE PALMS D
by RAJKUMARI GULAB CHOITHRAMANI
GAT NO 286 P, Borhadewadi, BORHADEWADI, 412105
Sept 2022
Possession
63.6%
Built
2
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Mar 2021, now proposed Sept 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 63.6%.
Official RERA facts
- Registration
- P52100002144
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2022originally March 2021
- Construction
- 63.6% complete
- Units sold
- 0 of 0
RERA complaint record2 records
- ComplaintCC00500000002304221 May 2019Sachin banait vs Rajkumari Gulab Choithramaniilovepdf_merged (2).pdf on MahaRERA
- Misc. applicationCC00500000002304221 May 2019Sachin banait vs Rajkumari Gulab Choithramaniilovepdf_merged (2).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths70%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains70%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting60%
Energy managemcnt60%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parking50%
Building & registration
- RERA registered
- Jul 2017
- Floors
- 10
Buyer community
Connect with other buyers and owners of SOLITAIRE PALMS D โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SOLITAIRE PALMS D. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.