Under construction

SOLITAIRE PALMS D

by RAJKUMARI GULAB CHOITHRAMANI

GAT NO 286 P, Borhadewadi, BORHADEWADI, 412105

Sept 2022
Possession
63.6%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2021, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 63.6%.

Official RERA facts

Registration
P52100002144
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally March 2021
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains70%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting60%
Energy managemcnt60%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parking50%

Building & registration

RERA registered
Jul 2017
Floors
10

Buyer community

Connect with other buyers and owners of SOLITAIRE PALMS D โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SOLITAIRE PALMS D. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.