Dec 2026
Possession
78.8%
Built
24
Complaints
217
Units
High risk
- Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ the strongest enforcement action on record.
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- 24 RERA complaints. 24 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100002155
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 78.8% complete
- Units sold
- 169 of 217
RERA complaint record24 records
- ComplaintCC126042004 Jul 2026Neelkanth Basappa Kanikeri vs Tanishq Realities
- ComplaintCC1260098123 Feb 2026Archana Pund vs Tanishq Realities
- ComplaintCC1250245118 Jul 2025Rajasekhar Rao Gane vs Tanishq Realities
- ComplaintCC125018819 Jun 2025Chandan Kumar Jha vs Tanishq Realities5 CC12501881.pdf on MahaRERA
- ComplaintCC1250133822 Apr 2025Roshani Swapnil Rawale vs Tanishq Realities39 CC12501338 Roshni Rawale vs Tanishq Realities.pdf on MahaRERA
- Misc. applicationCC1250133822 Apr 2025Roshani Swapnil Rawale vs Tanishq Realities
- Misc. applicationCC00500000028998530 Dec 2023V.T. Palresha &co. PRIVATE LIMITED vs TANISHQ REALITIES
- Misc. applicationCC00500000028998630 Dec 2023ENVIIRO BUILDMATE PVTLTD vs Tanishq Realities
- ComplaintCC00500000028998530 Dec 2023V.T. Palresha &co. PRIVATE LIMITED vs TANISHQ REALITIESOrder 289985.pdf on MahaRERA
- ComplaintCC00500000028998630 Dec 2023ENVIIRO BUILDMATE PVTLTD vs Tanishq RealitiesOrder 289986.pdf on MahaRERA
- ComplaintCC00500000026932325 Aug 2023Mr. Purushottam Manphoolsingh Ranjan vs M/s.Tanishq Realities Thr its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha MateSr 12 Draft order CC005000000269323 Mr Purushottam Ranjan & Anr Vs MS TANISHQ REALITIES signed.pdf on MahaRERA
- Misc. applicationCC00500000026932325 Aug 2023Mr. Purushottam Manphoolsingh Ranjan vs M/s.Tanishq Realities Thr its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha Mate
- ComplaintCC0050000001572629 Sept 2022Sunil Ramchandra Rathod vs M/s Tanishq Realities8 Sr 10 Draft of Order CC005000000157262 Tanishq Realities VS Sunil Ramchandra Rathod.pdf on MahaRERA
- Misc. applicationCC0050000001067418 Mar 2022Mr. Bhaskar Sarjerao Patil vs M/s Tanishq Realities Thro. Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d) Sneha Mate
- ComplaintCC0050000001067418 Mar 2022Mr. Bhaskar Sarjerao Patil vs M/s Tanishq Realities Thro. Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d) Sneha MateScanned Order CC005_106741.pdf on MahaRERA
- ComplaintCC00500000010665323 Feb 2022Mr. Nitin Giridhar Firke vs M/s.Tanishq Realities Thr.its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha MateDraft disposal order in CC005000000106653-APPL-RT-1 signed.pdf on MahaRERA
- Misc. applicationCC00500000010665323 Feb 2022Mr. Nitin Giridhar Firke vs M/s.Tanishq Realities Thr.its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha Mate
- ComplaintCC00500000010650320 Jan 2022Sumit Sajjan Waghmare vs Tanishq Realities Thr its Partner's a) Ramesh Talekar b) Balasaheb Talekar c) Amol Mate d)Sneha MateSr 4 Order review application in CC-5-106503 signed.pdf on MahaRERA
- Misc. applicationCC00500000010650320 Jan 2022Sumit Sajjan Waghmare vs Tanishq Realities Thr its Partner's a) Ramesh Talekar b) Balasaheb Talekar c) Amol Mate d)Sneha Mate
- ComplaintCC00500000006468517 Oct 2020Mr. Nandkishor Sudhakar Kharad vs M/s. Tanishq Realities Through its Partner & Authorised Signatory Mr. Ramesh Dnyanoba TalekarCC005000000064685_NANDKISHOR SUDHAKAR KHARAD Vs MS TANISHQ REALITIES _Disposal Order- signed.pdf on MahaRERA
- Recovery warrantCC00500000006471612 Oct 2020Rajesh Vishwanath Raut vs M/s. Tanishq Realities Through its Partner & Authorized Signatory Mr. Ramesh Dnyanoba Talekar
- ComplaintCC00500000006471612 Oct 2020Rajesh Vishwanath Raut vs M/s. Tanishq Realities Through its Partner & Authorized Signatory Mr. Ramesh Dnyanoba Talekar64716 order.pdf on MahaRERA
- Misc. applicationCC00500000006471612 Oct 2020Rajesh Vishwanath Raut vs M/s. Tanishq Realities Through its Partner & Authorized Signatory Mr. Ramesh Dnyanoba Talekar
- ComplaintCC0050000000540156 Feb 2020Rajesh Ramchandra Bhide vs Ramesh Dhondiba TalekarCC005-54015 dated 30-08-2021.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains92%
Landscaping & Tree Planting92%
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 12
- Unit mix
- 217 res ยท 0 comm
- Architect
- Mangesh Gotal
Buyer community
Connect with other buyers and owners of Tanishq Vlasta โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Tanishq Vlasta. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.