Under construction

Undri City Centre

by UKT Constructions

Survey no. 5, H No 1/2, 2/4/2, 2/4/3P, 2/4P, Undri, 411028

Oct 2020
Possession
100%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Sept 2018, now proposed Oct 2020 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.

Official RERA facts

Registration
P52100002700
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally September 2018
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of Undri City Centre โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Undri City Centre. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.