Jun 2023
Possession
25.4%
Built
3
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2019, now proposed Jun 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 25.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Official RERA facts
- Registration
- P52100002705
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally June 2019
- Construction
- 25.4% complete
- Units sold
- 0 of 0
RERA complaint record3 records
- ComplaintCC00500000026948121 Sept 2023VILAS RAJARAM SHINDE vs M/s. Sangam RealtyCC005000000269481.pdf on MahaRERA
- ComplaintCC00500000026948221 Sept 2023CHANDRAKANT TUKARAM KARADKAR vs M/s. Sangam RealtyCC005000000269482.pdf on MahaRERA
- ComplaintCC00500000026942311 Sept 2023DATTARAM BALARAM SHINDE vs Sangam RealtyCC005000000269423.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths10%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parking10%
Compound Wallnot started
Retaining Wall90%
Earthworkdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
Buyer community
Connect with other buyers and owners of Playtor Paud D- Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Playtor Paud D- Phase 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.