Under construction

PARVATARA PHASE 2

by Saakshi Constructions

Plot No. 74/1B/1, Kiwale, Pune, Kiwale, 412101

Dec 2027
Possession
71.5%
Built
0
Complaints
116
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100002707
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2022
Construction
71.5% complete
Units sold
94 of 116

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
20
Unit mix
90 res ยท 26 comm

Buyer community

Connect with other buyers and owners of PARVATARA PHASE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARVATARA PHASE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.