MANTRA CITY 360 PHASE03
by MANTRA ISLAND HOMES TALEGAON LLP
S.no.389/1/A, Talegaon Dabhade, Pune- 410506, TALEGAON, 410506
- Possession delayed ~2 yrs. Originally promised Oct 2019, now proposed Oct 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 88.2%.
Official RERA facts
- Registration
- P52100002880
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2021originally October 2019
- Construction
- 88.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 2
Buyer community
Connect with other buyers and owners of MANTRA CITY 360 PHASE03 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MANTRA CITY 360 PHASE03. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.