Mar 2022
Possession
86.8%
Built
46
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2020, now proposed Mar 2022 per the RERA filing.
  • 46 RERA complaints. 46 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 86.8%.
  • Promised amenities not started. Kids Play Area is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100003059
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally September 2020
Construction
86.8% complete
Units sold
0 of 0

RERA complaint record46 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting50%
Street Lighting90%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Open Parking85%
ZEN GARDENnot started
Tree Plaza with sitting areanot started
Therapeutical Walking Pathdone
MULTI PURPOSE PLAY AREAnot started
Multi Activity Lawn50%
Maze Gardendone
JOGGING TRACK50%
INDOOR GAMESnot started
FOREST TRAIL GARDENSnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of XRBIA EIFFEL CITY CHAKAN PH2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching XRBIA EIFFEL CITY CHAKAN PH2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.