Under construction

ADORA

by NEST KRISALA ASSOCIATES

SURVEY NUMBER 61/2/1, Pimpri Chinchawad (M Corp.), 412101

Mar 2019
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 81.8%.

Official RERA facts

Registration
P52100003141
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths66%
Water Supply66%
Sewerage (Chamber, Lines, Septic Tank , STP)66%
Storm Water Drains66%
Landscaping & Tree Planting30%
Water conservation /Rain water harvesting66%
Energy managemcnt66%
Fire protection and fire safety requirements66%
Electrical meter room, sub-station, receiving station20%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of ADORA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ADORA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.