Guardian Eastern Meadows - Phase 2

by Guardian Promoters & Developers Private Limited

Plot A, Gat No. 1344/1/1 and 1344/1/2, Haveli, 412207

Dec 2026
Possession
62.3%
Built
5
Complaints
227
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100003157
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
62.3% complete
Units sold
147 of 227

RERA complaint record5 records

  • ComplaintCC1260141614 Mar 2026
    ASMITA ASHWINKUMAR HATWAR vs Guardian Promoters & Developers Private Limited
  • ComplaintCC1260100924 Feb 2026
    SHIVKUMAR SINGH PUNDIR vs Guardian Promoters & Developers Private Limited
  • ComplaintCC0050000001066345 Mar 2022
    Proposed Guardian Eastern Meadows CHS vs Guardian Promoters & Developers Pvt. Ltd. though Mr. Manish Murlidhar Sabade
    Order of Guardian CHS.pdf on MahaRERA
  • ComplaintCC00500000009596720 Sept 2021
    Mrs. Shraddha Jitendra Dolare before Marriage Miss Shraddha Madhukar Hingase vs Guardian Promoters & Developers Private Ltd. Thr. its Directors a. Manish Sabade b. Manish Soman
    Order of Shraddha Dolare-3-08-2023.pdf on MahaRERA
  • ComplaintCC00500000001070116 Dec 2017
    Mahesh Vilasrao Dube vs Guardian Promoters and Developers Private Limited
    CC 005 10701 Mahesh Vilasrao Dube.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
15
Unit mix
227 res ยท 0 comm
Architect
Vikas Achalkar Vikas Achalkar

Buyer community

Connect with other buyers and owners of Guardian Eastern Meadows - Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Guardian Eastern Meadows - Phase 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.