Under construction

ARCHANA KOHINOOR GLORY

by KOHINOOR GLORY

S NO 38/2B 3A/2, S NO 38/2B 3A/3, MOHAMMADWADI, 411060

Mar 2019
Possession
76.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 76.8%.

Official RERA facts

Registration
P52100003656
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
76.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply51%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Landscaping & Tree Planting50%
Street Lighting25%
Treatment And Disposal Of Sewage And Sullage Water30%
Water conservation /Rain water harvesting25%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station25%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of ARCHANA KOHINOOR GLORY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ARCHANA KOHINOOR GLORY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.