Under construction

Vertical Oriana Phase I

by Vertical Infra

Survey No.7/1A, 2A, 2B, Mundhwa, 411036

Dec 2018
Possession
51.5%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 51.5%.
Ambernath / BadlapurValue

The value frontier beyond Kalyan โ€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100003700
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
51.5% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station20%
Open Parking30%
Solar Water Heater Systemnot started
Toddlers play area & Creche40%
Garbage Chute40%
Lift Installationnot started

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of Vertical Oriana Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vertical Oriana Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.