Under construction

NYATI ESTEBAN I

by NYATI REALTORS LLP

S No 4 and 21, Mohammaswadi, 411060

Mar 2022
Possession
79%
Built
14
Complaints
0
Units
High risk
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 79%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100003767
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally June 2021
Construction
79% complete
Units sold
0 of 0

RERA complaint record14 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Internal Roads & Footpaths75%
Internal Roads & Footpaths20%
Internal Roads & Footpaths60%
Water Supply65%
Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Storm Water Drains70%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Planting70%
Street Lightingnot started
Street Lightingnot started
Street Lighting65%
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal40%
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvesting70%
Energy managemcnt65%
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirements75%
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving station65%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Space80%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of NYATI ESTEBAN I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NYATI ESTEBAN I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.